They have drilled to 32m, lined with the plastic pipes and filled around them with fine gravel. The water has risen 25m back up the borehole. Their pump is down at about 30m and we need to flush water through for a couple of days. We will only need a small pump rated at less than 0.5kw.
Interesting that they didn't get down to gritstone which could be why the water looks clear of iron.
They will be back on Monday to bring the pressure vessel, clear up and move the vehicles off-site. The pump might take a few days to arrive.
Photos later once Col has recovered from a stressful day watching and recording progress!