I started the morning by taking a bit more off the gib, greasing it with Molyslip and popping it back in.
Then I got my act together for drilling and tapping the holes in the chests for the valve rod gland and the steam inlet to the chest. Have a very careful think and double check everything before you mark them!
Normally I'd do this under the pillar drill but I haven't got enough headroom there for the 11.5mm tapping drill so I took the collet chuck off and installed the keyless chuck, easier than swapping collets.
In case you're wondering.... I made the fatal error of trying the finished thread entry with my finger and got a chip 1/8" long buried in my left index finger. The Roebuck splinter tweezers are an important item in my shed! Luckily I found it first time and pulled it out.
Both chests drilled and tapped 1/2" x 26tpi.
Then I started on the lids. I'm not milling for size just squareness. I need them partially finished before I start measuring and marking....
Both long sides done on each of them.
Then I set up for cutting the ends square and knocked off, I've done enough this morning!